Panelists at Broadband Nation Expo 2026 addressed fiber, labor and permits collide ahead of the 2027. (Art by Midjourney for Fierce)
  • AFL expects no real relief in fiber supply until the 2029-2030 timeframe
  • Clearfield has begun rolling out price increases after absorbing costs in 2026
  • Shortages of splicers and crews, uneven local permitting and BEAD reimbursement terms could slow projects as the build season ramps up

BROADBAND NATION EXPO, NEW ORLEANS – Executives from Clearfield, AFL, TAK Broadband and the legal community say early forecasting, flexible designs and open communication are the best defenses as BEAD and data center builds compete for the same supplies and crews.

Indeed, broadband builders are heading into a crunch. With BEAD-funded deployments, data center construction and energy-grid projects all drawing on the same pool of fiber, equipment and skilled crews, a panel at Broadband Nation Expo warned that 2027 could test even well-prepared network operators.

“There’s scarcity in fiber and labor,” Marc Temple, VP of channels and strategic alliances at Clearfield, said during the “Bracing for Bottlenecks: When all the builds hit the same shot clock,” panel moderated by David Bronston, special counsel at Phillips Lytle.

Panelist Will Miller, director of global product management for broadband at AFL Global, agreed and said new capacity will take time to arrive.

Estimates for bringing new fiber preform draw capabilities online range two to five years, he said. “We don’t really see relief in the fiber market really coming to pass until probably the 2029-2030 time frame. … As long as supply remains tight, pricing is probably going to remain … at an elevated level.”

Temple said Clearfield absorbed much of the cost pressure in 2026 but could not do so indefinitely. “We have started to roll out price increases,” he said, adding that the company is looking at consolidating demand and helping customers bring some work in-house.

Build America, Buy America (BABA) rules add a further constraint for BEAD projects, the panelists said. Temple said data center builders “don’t really have the BABA constraints,” while BEAD fiber must be made in the U.S. He advised the room to forecast early, minimize the fiber in the design and look beyond usual distributors.

“I know loyalty is great, but if you need that fiber, you’re going to have to go outside of your normal channels to look for it,” Temple said.

Labor: creative solutions needed

Kimberly McKinley, chief of staff at TAK Broadband, said labor availability varies sharply by market. “Some of the markets that we’re in, we have no labor shortages. Other markets, we have extreme labor shortages, and we’re having to move people from different markets to cover those. But that comes with cost as well.”

She said the market may tighten once BEAD funding flows. “I don’t think it’s as dire right now than it will be in six months.” TAK Broadband runs a training facility in Arizona to prepare splicers on short notice, she added.

Data center demand is still intense. Miller said he recently visited a Texas campus of more than one gigawatt, with a larger one 15 minutes away. “I’ve never seen a ribbon splicer demand like this in my life,” he said, adding that he does not expect a slowdown for at least two years.

Some customers are shifting labor off the field. “Because of the shortage of splicers out in the field, customers are asking to bring some of that labor in-house into the factory,” Temple said, so deployment is “just plug and play.”

McKinley also criticized last-minute scope changes. “They say we’re going to do a 150,000 home build … and then they switch it last minute after we’ve already stacked up … and now we’re doing 75,000,” she said. “It’s just communication that is really important.” She also warned that squeezing contractors on price carries risk: “We are seeing construction companies go under for that reason because you can’t squeeze something that isn’t there.”

Contracts, permitting and politics

Coran explained that BEAD subgrantee agreements can pay on milestones, on reimbursement or on a hybrid of both. The hybrid model can strain cash flow, he said. “You’re carrying essentially the BEAD money plus your own match.” He said some providers have considered walking away, and that operators should negotiate provisions on reporting, testing and delays. He noted that some states allow pre-signing expenses to be reimbursed.

On permitting, McKinley said the FCC’s 120-day approach needs careful scrutiny. “80 to 90% of the permits come in in a timely manner. We’re trying to really manage 10%,” she said, cautioning about unintended consequences. She urged contractors to build trust with local officials. “Treating them like humans and walking in and having a cup of coffee with them will go a long, long way.”

Coran said permitting reform is a priority for the current Congress and administration, but the calendar is tight. The Senate passed the Bipartisan American Affordability and Jobs Act of 2026 (BAAJA) 73 to 25, but a continuing resolution expires December 11. He also suggested smaller providers consider alternatives such as fixed wireless where appropriate, which regulators might prefer over waivers or cost modifications.

Final thoughts: stay flexible

Asked to sum up the good, the bad and the ugly of bottlenecks in 2027, the panelists settled on adaptability. “Stay positive,” Coran said.

“Be creative and pivot,” said McKinley.

Temple said the good news is that “the demand is real.”

Miller offered the most pointed take. “The ugly is the word that I keep saying again, it’s allocation. I’m so sick of the word,” he said. “How can we turn the bad to a good? Flexibility.” He urged operators to work with vendors, contractors and legal advisers “with the intent” of staying flexible.

Read the latest news on broadband from Fierce Network: